Eppalock to Sandhurst Augmentation

> Pipeline Diagram

The diagram shows the schematic location of the pipeline. > click here

 

> Pipeline Route

At a property level, the works were confined to the existing water supply easement. The new pipelines are within the existing easement corridor, parallel to and offset from the existing pipeline. No works or clearing took place beyond the easement. The creation of additional easements was not required.

 

> Pipeline Construction

Construction of the Stage 1 pipeline was completed in July 2009. The new pipeline was pressure tested and then joined to the existing pipe in early August 2009. The final works to finish the air and scour valves and surface restoration were completed by the end of August 2009.

Construction of Stage 2A started in November 2009 and was completed in May 2010.

Construction of the Stage 2B works commenced at the western end of the stage in July 2009 and was completed in November 2009 with the exception of the connection to the existing pipeline, which was completed in May 2010.

Back to project Home Page > click here

 

A view down a section of the water supply easement through which the duplicated sections pipeline will be constructed

A different section of the water supply easement during onstruction (image taken 25/11/2008)

 

 

 

 

Permanent Water Saving Rules Coliban Water Blog Reservoir Levels 5-year Water Plan Let's Talk Sustainability’ Water Restrictions Smart Gardens Bushfire Readiness Water Outlooks

Paying Your Bill

For all your Coliban Water bill payment options,
please click here.


Fault and Emergency

For all enquiries including 24 hour emergency service call:

1300 363 200


visit savewater.com.au


Coliban Water

37-45 Bridge Street,
Bendigo VIC
ABN 96 549 082 360

Home | Privacy Statement | Disclaimer | Conditions | Site Map | Contact Us | Feedback |   Copyright © 2008-2012 Coliban Water